DDG 51 Flight III Program Update with Capt. Mark Vandroff at SAS 2016
27K views
Dec 19, 2023
NAVSEA briefing during Sea-Air-Space 2016: DDG 51 Program Update with Capt. Mark Vandroff, Major Program Manager, DDG 51 Program Office, PEO Ships
View Video Transcript
0:00
Thank you all for coming to this. I've got a few slides. I'm looking very much forward
0:21
to a good question and answer. I'll give you an update on where the DDG 51 program is today
0:27
We've got a lot of exciting things going on. You can see just there on my slide, that's
0:34
two ships at two different shipyards, both of them in the water, both of them in their
0:40
final throws of testing, and both of them will be going to sea for the first time sometime
0:46
later this summer. I'll talk a little bit about where we were to where we are. This
0:52
is a special week for me. It was five years ago this week. Where's Pete? Right, my predecessor
1:01
Pete Lyle in the back there. It was five years ago that Pete and I turned over and that I've
1:08
been the DDG 51 program manager. The team has been phenomenal. We'll talk a little bit
1:15
about what's happened over that time. We'll talk about the profile, a little bit about
1:24
where we are in production, what we're doing with Flight 3, and then again I'll be happy
1:29
to take any questions. This is my favorite chart to put up here. I only have half an
1:35
hour and I really only want to talk for ten minutes, but my staff especially knows I can
1:40
put that chart up and I can start talking for a couple of hours just to this chart
1:45
But I'll use it to refresh everyone's mind there. After the initial 62 ships were appropriated
1:53
built, and delivered to the Navy and currently in service, starting in FY10, we restarted
1:57
the program. Four ships over three fiscal years, 10, 11, and 12. Those four ships, DDGs
2:03
11, 13, 14, 15, 16, all of them in construction now, all of them very far along in construction
2:10
I believe 113 and 115, the first ships at Ingalls and Bath will deliver this year with
2:16
114 and 116 soon on their heels behind them. Then you get into the third multi-year. Not
2:24
very many programs are in production so long that they've done three different multi-year
2:29
procurements, but this is now the third for the DDG 1s. FY13 through 17, those 10 ships
2:37
the first few are in the early stages of production both at Bath and Ingalls, although you'll
2:43
see 117 not so early anymore. She's starting to come along really nicely. She looks like
2:48
a ship now. She'll go in the water early next year. Then with that, and we'll talk a little
2:55
bit about FY3, the program is so successful that in FY16, Congress decided to add most
3:02
of the funding for an extra ship there in FY16. Then starting in 16 into 17, we'll implement
3:10
the FY3. We've also started the initial planning and early work towards a fourth multi-year
3:17
procurement in FY18 and beyond. That's where we are today with the program
3:25
I'll just talk about where we are at the two shipyards, give everyone an update. DDG 113
3:32
we had her Aegis light off late last year. She's in the throes of the test program. These
3:40
ships, we've always historically done three sea trials on Aegis ships. Then during the
3:47
latter part of the first 62, we collapsed those all the way down to a single unified
3:53
sea trial, what we called a super trial, where we would do builders and acceptance trial
3:56
all in one week event. For the first few ships of the restart, we've gone back to the three
4:01
trials, an alpha for HM&E, seaworthiness, survivability, a trial Bravo, which was very
4:09
combat systems focused, where we would do missile firings and gun firings. Then finally
4:14
an acceptance trial, which is where NSERV comes and evaluates the ship for acceptance
4:19
into the Navy. Trial alpha 113 will be later this summer. You can see if she went aboard
4:25
her today, she's starting to look like a really complete ship coming through the last part
4:29
of her testing. 114, great launch, great christening. We have the Aegis light off, which is scheduled
4:38
for the early part of next month. They're going to make that on time. Last time I was
4:42
at Ingalls, the ship there on 114 was coming along beautifully to be ready for that milestone
4:50
Then she'll go to sea early part of next year. 117 had a great keel laying last year, and
4:56
we expect her to go in the water the early part of next year. She's really starting to
5:00
look, if you had a better picture there for 117, that's a good picture. You can see the
5:05
aft deck house going on. If you took back and had a larger picture of her, seeing the
5:10
whole ship, you can see, especially over time, she's gone from the initial few blocks out
5:15
on the building ways to now she's almost entirely built out. The only thing left to put on her
5:20
is the mast. Then 119, start of fabrication, she'll have her keel laying here next month
5:27
so really starting to get into good production on 119 down at Ingalls. At Bath, 115, which
5:34
is their first ship, they had her ALO again late last year in the throes of her test program
5:42
She's got a trial office scheduled again for late this summer as well with the delivery
5:49
sometime before the end of the year. 116, Bath, because of their facility, they keep
5:55
their ships on land a little longer in the production compared to Ingalls, so 116 still
6:01
on land, but again, you can see all put together looking very much like a ship marching towards
6:07
startup combat systems testing later this year and launch again at the end of this year
6:15
Then 118, start of fabrication with a keel laying sometime next year and then progressing
6:22
similar to 116 and 115 after that. Again, ships coming along very nicely at both yards
6:30
So let me talk a little bit now about the future, and I sound a little bit like a broken
6:36
record because I've given this pitch a lot and it really hasn't changed. I used to think
6:43
well, something has to have changed or I'm not going to be very interesting when I talk
6:47
about Flight 3. Then I realized it's actually good that this hasn't changed because it means
6:52
that we're on track. So Flight 3, the new radar, SPY-6, the DDG-51 fielding of the air
7:04
and missile defense radar. What do we do to the ship besides changing out the radar? We
7:09
do three things, three basic things. New power or modified upgrade power, so we go from three
7:16
megawatt generators to four megawatt generators and a new 4160 bus tied back into the 450
7:23
bus to service the radars. Cooling, replace the 200 refrigeration ton plants with the
7:30
new high efficiency 300 ton refrigeration plants. And then finally, weight and KG, we
7:36
thicken up the scantlings, we thicken up the keel, we thicken up some of the low weight
7:41
in order to bring the center of gravity back down where it needs to be. And then in order
7:45
to give us the weight to take that extra weight, the stability, we widen the stern
7:49
a little bit. Move a few berthing compartments around, a little bit of change in the way
7:54
of the internal piping. And when it's all said and done, that's a Flight 3. That's going
8:00
to be the third ship here in FY16. We had always planned that one of the FY16 ships
8:06
was going to be the first Flight 3. When Congress in their wisdom plussed us up from two to
8:12
three, said, okay, that plus-up ship is going to be the Flight 3. The first two base will
8:16
be two A's. And that's coming along very well. So the design for this, we're in the throes
8:22
of detailed design. Both yards, Ingalls and Bath, working that. At both yards, we are
8:28
on schedule, we are on budget for that detailed design. A brief aside, someone who I will
8:38
not name, told me with a straight face, they said this as if it were news to me. They said
8:50
we see that you are on track, you are on schedule with the detailed design for Flight 3. But
8:55
we are worried that if the design falls behind, you could experience cost growth and schedule
9:01
delay. And I said, right. I said, yes. Like every other project ever undertaken in human
9:10
history, if you fall behind, you will have cost growth and schedule delay. That is true
9:16
The Flight 3 does not. It's a great idea and a great design, but the laws of physics still
9:21
apply to it. I was not able to get around the laws of physics or the laws of economics
9:26
with Flight 3. It's still part of it. But the good news is that both yards are doing
9:34
great on the design. They're both doing great on it. We're on track and we're very pleased
9:39
with how they're doing the detailed design. So let me talk a little bit about where we
9:44
are with the systems that are my part of it. If you want to know where we are on SPY-6
9:51
I will tell you we're on track. And if you want more details on that, my colleague, Captain
9:56
O'Connor, who's the radar program manager in IWS, I don't know if she's speaking here
10:01
this week, but she's got it. You know, she's the expert on that. She's delivering me the
10:06
radar. The first piece, which is the generator, this is a modified repeat of the DDG-1000
10:13
generator. DDG, which in itself is mostly in the engine case, a mod repeat of the original
10:19
Flight 2A generator. The engine that Rolls-Royce puts in that is a DDG-51 engine with a couple
10:28
of extra compressor stages in order to get you the extra power to go from 3 megawatts
10:32
to 4 megawatts. So that engine has been through its preliminary and critical design reviews
10:37
and we're expecting in the fall of 2017, the first of the units to go to our land-based
10:44
engineering site at NAVSES, or excuse me, Naval Surface Warfare Center, Philadelphia
10:49
not NAVSES anymore. It's its own echelon for command. And to start our land-based testing
10:55
there with deliveries to the shipyard soon after that. The 1000-volt power supply, DRS-1
11:01
a very spirited competition to build that, has been through preliminary and critical
11:07
design review, completed its production readiness review, and is now in production. And it'll
11:12
be delivering both to the Elbess in New Jersey and to Wallops Island out in Virginia so
11:18
that there could be a unit to tie in the power on the power side and then another unit to
11:23
test the radar against so that if we don't get a full end-to-end check out before it
11:28
goes to the ship, we've at least checked out all the interfaces ashore before we take
11:32
that to the ship. Again, the systems engineering here in order to reduce risk so that when
11:37
we take this radar to the ship, we have high confidence that all the things that need to
11:41
support the radar, the power, the cooling, the space, everything that that radar requires
11:48
we're going to have high confidence that we can deliver that. And then finally, we're
11:53
in the throes of first article testing, nearly coming to completion there this summer, into
12:00
the fall for the AC plant, and then we'll be ready to put that into production and start
12:05
delivering AC plants to our shipbuilders that are the new high efficiency AC plants
12:13
roughly another 100 tons per AC plant of cooling. And when I say ton, some people think
12:19
wait, that's a refrigeration ton. It's a measure of how much refrigeration a given
12:24
AC plant can put out. So that's kind of my brief in chief. I've got my summary there
12:34
I want to take slides, but I want to say one thing. Someone asked me, one of the reporters
12:44
asked me if I was going to make news. This might make a little of it, so. Getting ready
12:49
for this, and especially since this is the fifth anniversary of me being in the program
12:54
I went back and I looked at what all the different folks said when the program restarted
13:00
and I owe a huge debt to the leadership of the program before me. The team has been great
13:07
and we've had turnover in the team, and the new people have benefited from what the existing
13:14
folks and their solid foundation and the wisdom they put in place. But when the Navy made
13:22
the decision to restart the DDG 51 program, they put a budget request to Congress and
13:29
said, okay, we're restarting the DDG 51 program. This is going to be tough. We're going to
13:35
need, it's going to cost more than a regular DDG 51, and in 2010, the President's budget
13:42
requested $2,240,000,000 in 2010 to go forward and do the first ship, and was roundly criticized
13:55
by everyone who likes to be a pro at criticizing the Navy. That's not enough. There's no way
14:02
you can do that. You've obviously underestimated it. I think there was a GAO report at some
14:07
point soon after that that kind of listed, amongst other things, when they were talking
14:11
about the radar hull study, all the different risks of the restart. And whenever the Navy
14:17
tries to do something and comes in over budget, that'll make news. But I'm going to make news
14:21
in a different way. Every fall, we, the DDG 51 program and all the other shipbuilding
14:29
programs, has a review with the Navy budget office, ship by ship, what's that ship going
14:35
to cost, because the Navy budget office might have to move money around. And I looked at
14:40
what, in 113, that FY10 ship is essentially done. We've got a little testing, a little
14:47
fielding, but we're months away from delivering that ship to the Navy. It's essentially done
14:51
The costs are what they are. They're all known. And so the Navy had asked for $2.2, $2,240,000,000
14:59
So you would think that if we delivered it at $2,240,000,000, you know, $2,240,000,000
15:06
if that was our price today, you'd think we had done a really good job, right? You'd think
15:10
that would be great. You'd think that'd be worth writing about. Our review with FM, we
15:16
said final price of that ship, $2,100,000,000, $103,000,000, $137,000,000 less than what
15:24
we had estimated back then. Now, $100,000,000 of that was claimed a few years ago by Congress
15:31
and reprogrammed into the excellent use of giving us an extra ship in 13 when you saw
15:37
that. So some of those savings have been booked and applied to other Navy priorities. But
15:42
five years ago, six years ago, we said $2.2 billion. Today, we say 2.1. So when you read
15:49
about, oh, there's no way that they're going to bring in the flight three for what they
15:53
say they're going to bring in. The Navy's always cost more than what they say. I want
15:58
to go back to the DDG restart and say, no, sometimes we get it right. Sometimes it takes
16:03
a little luck. It takes a whole lot of hard work by a whole lot of people, both on the industry side and the government side. But sometimes the Navy does get it right. And
16:11
maybe that'll make a little news in and of itself. So with that, I will take your questions
16:22
Questions, comments, brief alternate speeches. Shell. So, right. So for the flight three, you'll have two buses connected by transformers
16:38
right? A high voltage, or it's actually medium and low. So you have a medium voltage, 4160
16:43
volts. Power will be generated at 4160. The radar will be fed at 4160. And then the 450
16:50
existing loads will be serviced by stepping that down with transformers and then using
16:55
the existing 450 infrastructure. Right. So we'll step down, step. Yeah, you'll step down. I don't have it in backup. I actually
17:05
have a great slide that shows the existing electric plant and then the additional. But
17:10
right. Thank you, Shell. Hi. Dan Gaff of Aviation Week. In addition to the SPY-6, what happens on the flight three
17:27
with regards to the missile illuminators in the earlier aircraft? Same Mark 99. So still three illuminators, still Mark 99s. So those are as of yet unchanged
17:44
That's the baseline today. There are interesting things happening in illuminator technology
17:48
and there are interesting things that you're doing like on the DDG-1000, where if you have
17:54
an X-band phased array. So my X-band solution for tracking, search and track on the flight
18:01
three design now is a Spook 9B. Great radar, but it's not a phased array radar. And there's
18:07
you can't do some of the things that you could do, say, with SPY-3 as far as illuminator
18:11
uplink. So right now the flight three retains the existing three Mark 99 illuminators. In
18:20
a future iteration, because we're doing lots of things in future iteration, could you alter
18:25
the ship to take a fourth illuminator? That might be desirable. Yes, that would be a ship
18:29
design change. Could you alter the ship to put a phased array X-band solution and do
18:35
your illuminator uplink that way? Yes, you could. But that was one of the tenets of flight
18:42
three has been to bound our risk, right? We don't want to have such a radical change that
18:48
we end up making it too much of an investment at any one time. So the illuminator solution
18:54
for missile illumination on the flight three is the same three Mark 99 illuminators. Could
19:01
we take a step forward in the future? Yeah, but I want to make sure that I've got SPY-6
19:05
working and working right and doing that before we do something else to the platform. But
19:11
the answer is a long answer to a short question. Yes, sir
19:18
Yes, which shipyard do you think the first flight three will be at and do you know which
19:24
ship will be there? So let me answer that. You asked three questions. You only thought
19:32
you asked two, but you asked three questions. So I'll answer the easiest one first. That
19:39
third ship in FY16, based on the terms of the last LPD DDG 51 swap agreement between
19:50
Bath, Ingalls and the Navy, assigned a DDG amount of workload to Bath Ironworks. So the
19:56
current strategy is that's a Bath ship because the LPD 28 was an Ingalls ship. So that balances
20:04
out the workload and fulfills the swap. So that's the who. You said what? Let me go back
20:11
to that. I am now going to, someone again asked if I was going to make news, I am now
20:16
going to complain. Something I very rarely do. Write this down and take notes. This is
20:27
the multi-year as it exists now. DDG's 117 through 126 inclusive. 10 ships numbered
20:34
117 through 126. Because the Navy received from Congress economic order quantity AP for
20:44
buying things in groups of 10 or more than one, more than two, in the beginning of the
20:52
multi-year, we have already bought significant amount of components. For example, the vertical
20:57
launch system is already under contract and funded for these ships out here. It doesn't
21:01
change. The BLS Mark 41 doesn't change between flight two and flight three. Because we're
21:05
spending money against those ships, the advanced procurement, in the Navy's ERP accounting
21:10
system, we had to create the hull number and we had to create UX for the ship to account
21:15
for being spent against it. When Congress added this ship, they've now given us a ship
21:22
and you see there's purposely no hull number there. There will be at some point in the
21:26
future when I write this. You would think if we lived in a sane world, that I would
21:32
this is 123, this is 124, that I would just make that 125 and then I'd move all the numbers
21:37
so 126 and 127 became the FY17 ships. But the Navy's system currently for tracking stuff
21:46
and money against that stuff doesn't allow you to do that. So, I think what's going to
21:53
end up happening is you'll have 123, 124, and 127 as the three FY16 ships and 125 and
22:02
126 as the two FY17 ships and 127 will come out several months before 125 and 126. That
22:10
will confuse everyone. And every time I say this to anyone in senior Navy leadership
22:16
they look at me as if I have lost my mind, but I promise what I have told you is 100
22:21
accurate. My business manager is in the audience here today and she's looking at me and smiling
22:27
that everything I just said is right. Now the other question is what will it be named
22:32
We have names now up through 121. So, DDG 120 is named for the former senator from Michigan
22:42
recently retired SASC chairman, Senator Carl Levin. That was just announced. And then 121
22:49
is the Frank Peterson, a deceased senior Marine Corps general. So, I don't have names beyond
22:58
that whether or not between now and whenever the Secretary of the Navy chooses to name
23:03
any of these ships is up to him. Secretary of the Navy controls names. I get a letter
23:08
from the SEC NAV's office saying, these are the names of the ships, go put them on the
23:12
stern. So, I don't know what that 127 will be named yet. I have not received such a letter
23:17
But where we've got names out through 121. Electronic Warfare CWIP? I would love to talk about Electronic Warfare CWIP. So, the CWIP
23:44
program, just to kind of baseline everyone, is the Surface Electronic Warfare Improvement
23:49
Program being released in blocks. So, you have CWIP Block 1, CWIP Block 2, CWIP Block 3
23:55
eventually a CWIP Block 4. CWIP Block 2 is the baseline. So, let's do this one. So, CWIP Block 1 is basically a SLC-32 improvement. That takes
24:14
me up through 113 to 116. 117, I'm pretty sure I have that right. It's not 119. One
24:24
of my guys here from D5 wants to throw his hand up in the air and say, you're getting it wrong, sir. But I'm 90% sure 117 and follow is CWIP Block 2 on these ships. So, that's
24:36
the current baseline. CWIP Block 3 and CWIP Block 2 is a huge improvement over SLC-32
24:42
over the CWIP Block 1. It's a new EW system with tremendous new capability in that area
24:49
CWIP Block 3 takes that tremendous capability and then adds an active component to it. So
24:54
we are in the middle of working with our partners in POIWS and CO5 to study how we
25:01
would put CWIP Block 3 on DDG-51s, both the 2As and the 3s. That study, the technical
25:08
study is ongoing. So, that's certainly something that we plan to do in the future. But I don't
25:12
have it programmed. And I can't tell you, yep, it's these ships in back fit. It's these
25:17
ships in forward fit. I don't have that yet because we've got to finish the technical
25:21
study so we can make that decision. Any plans to integrate advanced anti-surface weapons on the flight 3
25:37
Advanced anti-surface weapons? So, right now it's the same anti-surface suite, excuse me
25:43
here. So, right now it's the same anti-surface suite as on the flight 2s. What you see here
25:51
is you've got the 5-inch gun. This is a CWIS-1B. So, that's a CWIS with an anti-surface. And
25:58
you can see it here, you've got the, whatever the current substantiation of the 25-millimeter
26:04
side guns for anti-surface defense. I can tell you we're looking intently at things
26:10
like laws and the next generation of laws for a directed energy weapon. I think the
26:16
additional power in the 4160 architecture will fit very nicely with that as that becomes
26:22
ready. I think we're looking, even in the back fit, we're looking at that for both the
26:27
2A and the 3 eventually. We don't have a program of record where I can say back on that
26:32
chart, yes, this ship is the first ship right now that's going to get a directed energy
26:37
anti-surface weapon. But it's something we're looking at intently and something we're very interested in. I could see that happening unlike that first flight 3 in a post-shakedown
26:46
availability type time frame. I think that would, by then you'd have a more mature
26:51
directed energy weapon there in the early 2020s. And we used to have two CWISs. That
26:58
now is a space and weight reservation for something the size of a CWIS. I think that
27:03
depending on what is available as the ships are being built and once the ship's commissioned
27:10
in a back fit, I think you'll see something go there that'll have both an anti-surface
27:16
and anti-air capability. Whether that's a directed energy weapon or another particular
27:20
kind of weapon remains to be seen. But there's a space and weight reservation up forward
27:24
where the forward CWIS used to be that would be used for something like that
27:31
Admiral back in the back there. One more question. The 127 is under current acquisition. Right
27:42
Flight 3s after that, are they going to be multiyear? So let me go back and I'll talk about that
27:48
I missed it. I apologize. No, no. That's great, sir. That's a good question. So I probably glossed over it. So
27:56
the only reason I want to be, let me be careful how I answer it, because any future acquisition
28:01
strategy would be until it's actually published and approved would be, as we say
28:07
it would be pre-decisional. But the notional SECNAV 30-year long range shipbuilding plan
28:12
that was just delivered envisions between 18 and 22, two ships a year in the Flight
28:19
3 configuration. And we've always said we were very happy with how we bought these 10
28:24
ships. So another 10 ship, five year, multiyear would be what would make sense. Now for that
28:31
we would have to go next year to Congress with the 18 budget and ask for legislative
28:35
authority to do that. And we would have to have that then as our acquisition strategy
28:41
I think that it would make sense to do that. That would be using things that were successful
28:47
in the past and the future. But until we actually come out with that ledge proposal, it's not
28:53
the official Navy policy yet. But I would say if you looked at the 30-year shipbuilding
28:57
plan, that would be a reasonable assumption based on what the Navy has said publicly so far
29:04
Any more questions? No time? Okay. All right. Thank you very much. Thank you all very much
29:14
Thank you
#Navy